Townshend Dam, West River

Townshend Dam, West River
 Drainage Area: 278 sq. miles 
 Channel Capacity: 9,000 cfs 
 Storage at Spillway Crest: 5.81 in / 32,900 ac-ft  
 Normal Pool: 21 Feet 
 Gate Settings for February 05, 2025 07:00 am Gate 1 Gate 2 Gate 3 Hydro Pos. Gate 5 Gate 6 Gate 7 Gate 8
  0.0 13.5 0.0 3        
Date Time
(Eastern)
Pool
(ft)
Storage
(%)
Storage
(ac-ft)
Tailwater
(ft)
Flow
(cfs)
Inflow
(cfs)
Precip
(in)
Air Temp
(F)
Feb-09 08:30 am 6.11 0.0 0 4.18 146 146 11.51 22.9
Feb-09 07:30 am 6.09 0.0 0 4.18 146 146 11.51 22.2
Feb-09 06:30 am 6.09 0.0 0 4.18 146 146 11.49 22.7
Feb-09 05:30 am 6.11 0.0 0 4.19 149 146 11.45 22.7
Feb-09 04:30 am 6.10 0.0 0 4.18 146 147 11.43 22.7
Feb-09 03:30 am 6.10 0.0 0 4.18 146 148 11.43 22.5
Feb-09 02:30 am 6.09 0.0 0 4.17 143 148 11.42 22.7
Feb-09 01:30 am 6.09 0.0 0 4.19 149 150 11.37 22.6
Feb-09 12:30 am 6.06 0.0 0 4.18 146 150 11.32 22.6
Feb-08 11:30 pm 6.04 0.0 0 4.19 149 150 11.25 22.8
Feb-08 10:30 pm 6.01 0.0 0 4.18 146 151 11.11 22.3
Feb-08 09:30 pm 5.96 0.0 0 4.19 149 151 11.05 23.1
Feb-08 08:30 pm 5.99 0.0 0 4.21 154 152 11.03 25.0
Feb-08 07:30 pm 5.99 0.0 0 4.20 151 152 11.03 25.6
Feb-08 06:30 pm 5.98 0.0 0 4.20 151 152 11.03 25.6
Feb-08 05:30 pm 5.99 0.0 0 4.21 154 152 11.03 26.7
Feb-08 04:30 pm 6.11 0.0 0 4.21 154 151 11.03 28.6
Feb-08 03:30 pm 6.34 0.0 0 4.22 157 150 11.03 31.2
Feb-08 02:30 pm 6.36 0.0 0 4.20 151 149 11.03 29.1
Feb-08 01:30 pm 6.19 0.0 0 4.20 151 148 11.03 28.5
Feb-08 12:30 pm 6.35 0.0 0 4.20 151 147 11.03 28.7
Feb-08 11:30 am 6.11 0.0 0 4.19 149 147 11.03 27.9
Feb-08 10:30 am 6.04 0.0 0 4.18 146 147 11.03 25.9
Feb-08 09:30 am 5.90 0.0 0 4.19 149 147 11.03 20.4
Feb-08 08:30 am 5.84 0.0 0 4.19 149 148 11.03 18.0
Maximum 24 Hour Drawdown Rate (10 feet/day): 0 cfs + Inflow (146 cfs) = 146 cfs
Report Generated February 09, 2025 01:40 pm