Edward MacDowell Dam, Nubanusit Brook

Edward Macdowell Dam, Nubanusit Brook
 Drainage Area: 44 sq. miles 
 Channel Capacity: 650 cfs 
 Storage at Spillway Crest: 5.45 in / 12,800 ac-ft  
 Normal Pool: 912 Feet NGVD 
 Gate Settings for July 12, 2024 07:00 am Gate 1 Gate 2 Gate 3 Gate 4 Gate 5 Gate 6 Gate 7 Gate 8
  3.0 0.0 0.0          
Date Time
(Eastern)
Pool
(ft)
Storage
(%)
Storage
(ac-ft)
Tailwater
(ft)
Flow
(cfs)
Inflow
(cfs)
Precip
(in)
Air Temp
(F)
Jul-13 03:15 am 911.29 1.3 186 2.53 47 51 27.20 69.4
Jul-13 02:15 am 911.27 1.3 184 2.51 45 40 26.93 72.9
Jul-13 01:15 am 911.27 1.3 184 2.51 45 40 26.93 72.6
Jul-13 12:15 am 911.27 1.3 184 2.51 45 40 26.93 72.4
Jul-12 11:15 pm 911.27 1.3 184 2.51 45 40 26.93 72.7
Jul-12 10:15 pm 911.27 1.3 184 2.51 45 41 26.93 73.5
Jul-12 09:15 pm 911.28 1.3 185 2.52 46 46 26.93 74.9
Jul-12 08:15 pm 911.28 1.3 185 2.52 46 46 26.93 76.5
Jul-12 07:15 pm 911.28 1.3 185 2.52 46 46 26.93 78.9
Jul-12 06:15 pm 911.28 1.3 185 2.52 46 41 26.93 80.2
Jul-12 05:15 pm 911.28 1.3 185 2.52 46 41 26.93 82.0
Jul-12 04:15 pm 911.28 1.3 185 2.52 46 41 26.93 83.3
Jul-12 03:15 pm 911.28 1.3 185 2.52 46 41 26.93 82.6
Jul-12 02:15 pm 911.28 1.3 185 2.53 47 36 26.93 83.3
Jul-12 01:15 pm 911.28 1.3 185 2.52 46 36 26.93 81.7
Jul-12 12:15 pm 911.29 1.3 186 2.52 46 41 26.93 81.0
Jul-12 11:15 am 911.29 1.3 186 2.52 46 41 26.93 79.0
Jul-12 10:15 am 911.29 1.3 186 2.53 47 41 26.93 77.4
Jul-12 09:15 am 911.29 1.3 186 2.53 47 41 26.93 77.6
Jul-12 08:15 am 911.30 1.3 188 2.53 47 47 26.93 74.6
Jul-12 07:15 am 911.30 1.3 188 2.53 47 47 26.93 70.7
Jul-12 06:15 am 911.30 1.3 188 2.53 47 47 26.93 65.7
Jul-12 05:15 am 911.30 1.3 188 2.52 46 47 26.93 64.8
Jul-12 04:15 am 911.30 1.3 188 2.52 46 47 26.93 65.7
Jul-12 03:15 am 911.30 1.3 188 2.53 47 47 26.93 67.5
Maximum 24 Hour Drawdown Rate (5 feet/day): 69 cfs + Inflow (51 cfs) = 120 cfs
Report Generated July 13, 2024 03:28 am